When should the code official be made aware of discrepancies found during a special inspection?

Study for the ICC Structural Steel and Bolting Certification Test. Prepare with flashcards and multiple choice questions, each accompanied by hints and explanations. Get ready to excel in your certification exam!

The correct answer is that the code official should be made aware of discrepancies found during a special inspection if they are not corrected by the contractor. This approach ensures that all issues that arise during the inspection process are adequately addressed and documented.

If a discrepancy is found and the contractor promptly resolves the issue, there may not be a need to escalate the matter to the code official immediately. However, if the contractor does not take corrective action, the involvement of the code official becomes essential. This communication helps maintain safety standards, ensures compliance with building codes, and allows for necessary interventions to be made before further construction activities proceed.

Other options, such as immediate reporting after discovery or at the end of the inspection process, might not reflect the practical workflow required in ensuring compliance and safety. Timely reporting is critical, but it is more effective when done in conjunction with the contractor's response to the discrepancy. Regular communication through status meetings does foster collaboration but may not adequately address urgent discrepancies that require immediate attention from a code official.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy